After the Eaton Fire
A January 2026 staff report to the Planning Commission says the Eaton Fire destroyed 185 structures in Pasadena, mostly single-family homes and accessory structures in Upper Hastings Ranch, Victory-Rose, Dundee Heights and the NATHA neighborhood. The windstorm that day also damaged roofs, fences and sheds across the city.
The Planning department set up an expedited, same-day, no-application permit for like-for-like repair and rebuilding of damaged roofs, fences and accessory structures, plus virtual consultations for displaced owners. Confirm the current process with the Permit Center before you promise a date.
The city's Fire Rebuild Fee Waiver covers city plan check and permit fees for red-tagged structures, including fire-damaged pools, covered patios, walls and fences, for owner-occupied single-family homes and condos as of January 7, 2025. It does not cover new structures that did not exist before the fire, such as turning a garage into an ADU. Pasadena Water and Power water service fees and a $1,000 refundable construction and demolition deposit still apply.
Sources12
Landmark districts: review comes first
The city counts 26 designated historic neighborhoods. In a landmark district, exterior changes need a Certificate of Appropriateness, and the city says the certificate is required before a building permit can be issued. The changes it reviews most often are window replacement, front porch reconstruction, additions, fences and new garages.
Plan for the time. Historic Preservation Commission review typically takes 6 to 8 weeks from submittal, minor projects reviewed by staff about 4 to 6 weeks, and the city says the process delays a building permit by about two months.
There is a useful exception for porch and deck work: on historic buildings the city can use the State Historical Building Code. The city's own example is a porch railing that is shorter than current code but can be kept instead of replaced.
Sources345
Permits online
Permit Center Online runs through the Citizen Self-Service portal for plan submittals such as additions and ADUs, and an Express Portal issues mechanical, electrical and plumbing permits within minutes. Inspections are scheduled online, with a call, text or email confirming the inspection window.
Sources67