Book inspections in CSS by midnight, then call the inspector
The city's site says Clovis permits run through its CSS portal (the EnerGov Self Service address on the city's forms), where you apply and request inspections. The Building Division's Inspection Requests sheet says it has no inspection request phone line and asks you not to call other divisions to book one. Online requests can be completed by midnight the day before.
If you need a time window, the Building page says to open Today's Inspections in the portal, find your inspector for the day, and call the number next to their name. A.M., P.M. or specific-time requests are considered but not guaranteed. The sheet also asks that the work be complete and per approved plans, with the approved plans and job cards on site. Rules and forms change, so confirm with the Building Division at (559) 324-2390 before you bid.
Sources34
A pool gets four inspections, in order
The Building Division's Swimming Pool Inspections handout lists four: pre-gunite (steel and bonding), pre-deck, pre-plaster or barriers, and final. On request, the first two can be combined and so can the last two. Steel, bonding and pressure-tested plumbing (at least 35 psi) are checked before gunite. The pre-deck inspection must be approved before any concrete deck is placed, so the deck crew can't get ahead of it. The handout also points to Clovis Municipal Code Section 8.10 for requirements it does not list.
Before the pool is filled, the handout says it needs at least two of the safety features listed in the California Swimming Pool Safety Act, and windows within 5 feet of the water's edge with glass lower than 60 inches above the walk must be tempered. At final, the city's Engineering Department (559-324-2370) has to finalize the encroachment permit. Put all of that in the pool schedule you show the homeowner, and confirm the current handout with the Building Division before you bid.
Source5
Patio covers and paying for a faster review
Clovis publishes a standard Patio Cover Plan (guideline sheet). It marks the patio not to be enclosed, caps rafter span at 10 feet when the rafters attach to the fascia, requires concrete footings sized from its table, and says setbacks must meet the residential zone. If your design fits that sheet, the submittal gets simpler. Anything outside it is a non-standard plan, so check with the Building Division first.
For jobs on a deadline, the Expedited Plan Review Policy says the goal is Building Division comments within 10 working days of a completed application. The policy says the typical charge is a minimum of four hours at $110 an hour, approval depends on a plans examiner being available, and the comments do not include Planning, Engineering or Fire. Ask the Building Division what the charge is today.
Sources67